Share Neerabup Terminal to Wangara Substation 132 kV Transmission Line – Application under the Metropolitan Region Scheme on Facebook Share Neerabup Terminal to Wangara Substation 132 kV Transmission Line – Application under the Metropolitan Region Scheme on X (formerly Twitter) Share Neerabup Terminal to Wangara Substation 132 kV Transmission Line – Application under the Metropolitan Region Scheme on Linkedin Email Neerabup Terminal to Wangara Substation 132 kV Transmission Line – Application under the Metropolitan Region Scheme link

Consultation closes 17 December 2026


Overview

A development application for transmission network works has been received by the Western Australian Planning Commission (WAPC) under Part 10 of the Metropolitan Region Scheme (MRS).

The proposal is a part of Western Power’s Clean Energy Link – North transmission upgrades and includes a double circuit 132kV overhead transmission line that spans 24 kilometres from the existing Neerabup terminal to ‘cut in’ with an existing Wangara substation 132KV line at the intersection of Ocean Reef Road and Wanneroo Road. This connection will complete the link to the Wangara substation. The transmission line will be supported by double circuit steel poles along the length of the route, between 18.5m and 25m tall. The distance between the poles will typically be 150m.

The development is valued at $150 million.

The application from Western Power is being advertised to seek public comments.


The process so far


Have Your Say 

You can have your say on the application by:

  • completing the online survey below, or
  • sending through your submission via post to Metro North - East Wanneroo team, Department of Planning, Lands and Heritage, 140 William Street, Perth WA 6001.

The last date to provide comments is 17 December 2026. Late submissions may not be accepted.

For more information about public consultation, including tips on making a good submission, please visit the Public consultation in the WA planning system webpage.

Consultation closes 17 December 2026


Overview

A development application for transmission network works has been received by the Western Australian Planning Commission (WAPC) under Part 10 of the Metropolitan Region Scheme (MRS).

The proposal is a part of Western Power’s Clean Energy Link – North transmission upgrades and includes a double circuit 132kV overhead transmission line that spans 24 kilometres from the existing Neerabup terminal to ‘cut in’ with an existing Wangara substation 132KV line at the intersection of Ocean Reef Road and Wanneroo Road. This connection will complete the link to the Wangara substation. The transmission line will be supported by double circuit steel poles along the length of the route, between 18.5m and 25m tall. The distance between the poles will typically be 150m.

The development is valued at $150 million.

The application from Western Power is being advertised to seek public comments.


The process so far


Have Your Say 

You can have your say on the application by:

  • completing the online survey below, or
  • sending through your submission via post to Metro North - East Wanneroo team, Department of Planning, Lands and Heritage, 140 William Street, Perth WA 6001.

The last date to provide comments is 17 December 2026. Late submissions may not be accepted.

For more information about public consultation, including tips on making a good submission, please visit the Public consultation in the WA planning system webpage.
  • By completing the form, you are consenting to the collection of your personal information for the purpose of providing feedback on this application. To understand more about the collection of your information, click here. 

    Complete Form
    Share Feedback Form - Neerabup Terminal to Wangara Substation 132 kV Transmission Line on Facebook Share Feedback Form - Neerabup Terminal to Wangara Substation 132 kV Transmission Line on X (formerly Twitter) Share Feedback Form - Neerabup Terminal to Wangara Substation 132 kV Transmission Line on Linkedin Email Feedback Form - Neerabup Terminal to Wangara Substation 132 kV Transmission Line link